SAP Activate Project Manager Certification Exam Details:

Sample QuestionsSAP Activate Project Manager Certification Sample Questions
Reference BooksACT100 (SAP S/4HANA 1809)
ACT200 (SEE COURSE DETAIL)
LevelAssociate
Schedule ExamSAP Training
Duration180 mins
Passing ScoreC_ACTIVATE13 - 65%
Exam CodeC_ACTIVATE13
Exam Price$550 (USD)
Number of Questions80
Exam NameSAP Certified Associate - SAP Activate Project Manager


SAP Activate Project Manager Certification Exam Topics:

Topic AreasTopic Details, Courses, BooksWeighting
Transition Path "New Implementation SAP S/4HANA On Premise"Describe concepts, landscape overview and specifics in Workstreams related to implementing SAP S/4HANA On Premise.

ACT100 (SAP S/4HANA 1809)

< 8%
SAP Activate ElementsProvide an overview of content, tools and methodology elements of SAP Activate Solution Implementation Framework.

ACT100 (SAP S/4HANA 1809)

> 12%
Transition Path "New Implementation SAP S/4HANA Cloud"Describe concepts, landscape overview, and specifics in Workstreams related to implementing SAP S/4HANA Cloud.

ACT100 (SAP S/4HANA 1809)

8% - 12%
Transition Path "System Conversion"Describe concepts, landscape overview and specifics in Workstreams related to “System Conversion” Transition Path.

ACT100 (SAP S/4HANA 1809)

< 8%
SAP Activate OverviewDefine factors influencing SAP Activate, its purpose and place among other frameworks.

ACT100 (SAP S/4HANA 1809)

> 12%
Agile Project PlanningDescribe the agile project roles and responsibilities and the preparation of the project including the planning, estimation, user story mapping and construction of backlog.

ACT100 (SAP S/4HANA 1809)
ACT200 (SEE COURSE DETAIL)

8% - 12%
Workstreams OverviewDescribe concepts, artefact flows, accelerators, tools and roles for each Workstream within SAP Activate Methodology.

ACT100 (SAP S/4HANA 1809)

> 12%
Agile Project DeliveryDescribe how the project team prepares release and sprint plans, and the structure and key activities in each sprint. Discuss key techniques used in agile projects.

ACT100 (SAP S/4HANA 1809)
ACT200 (SEE COURSE DETAIL)

> 12%
Transition Path "Selective Data Transition"Describe concepts, landscape overview and specifics in Workstreams related to “Selective Data Transition” Transition Path.

ACT100 (SAP S/4HANA 1809)

< 8%

 

NEW QUESTION 13
Which Value Chains does SAP Solution Manager 7.2 deliver?
There are 3 correct answers to this question.
Response:

  • A. Request-to-Fulfill
  • B. Hire-to-Retire
  • C. Cash-to-Order
  • D. Requirements-to-Deploy
  • E. Detect-to-Correct

Answer: A,D,E

 

NEW QUESTION 14
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
Response:

  • A. Prepare
  • B. Realize
  • C. Explore
  • D. Deploy

Answer: D

 

NEW QUESTION 15
What is the correct order of the SAP Activate Methodology phases?
Please choose the correct answer.
Response:

  • A. Plan -> Build -> Run -> Sustain
  • B. Prepare -> Discover -> Explore -> Realize -> Deploy -> Run
  • C. Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
  • D. Plan -> Design -> Build -> Operate

Answer: C

 

NEW QUESTION 16
When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?
Please choose the correct answer.
Response:

  • A. During the sprint retrospective
  • B. During the sprint review
  • C. During user acceptance testing
  • D. During the daily SCRUM meeting

Answer: B

 

NEW QUESTION 17
Which activity helps the Project Team add User Stories to the Product Backlog?
Please choose the correct answer.
Response:

  • A. Planning the User Acceptance Test
  • B. Assessing Project Risks
  • C. Conducting the Solution Validation workshop
  • D. Preparing a Project Schedule

Answer: C

 

NEW QUESTION 18
How many deliverables are a part of the Key Deliverable 'Project Initiation'?
Please choose the correct answer.
Response:

  • A. Three
  • B. One
  • C. Four
  • D. Two

Answer: C

 

NEW QUESTION 19
What Sprint types are part of the SAP Activate Methodology?
There are 3 correct answers to this question.
Response:

  • A. Foundational
  • B. Daily
  • C. Initial
  • D. Build
  • E. Firm-up

Answer: A,D,E

 

NEW QUESTION 20
What is the purpose of the scrumboard?
Please choose the correct answer.
Response:

  • A. To show the functional breakdown of the solution scope
  • B. To visualize team progress
  • C. To manage the resource load
  • D. To document the results of integration testing

Answer: B

 

NEW QUESTION 21
What does the Side-by-Side Extensibility Option mean?
Please choose the correct answer.
Response:

  • A. Transfer reporting to BW/4HANA
  • B. Have two SAP S/4HANA instances - one for standard code, and another for custom developments
  • C. Extensibility based on the SAP Cloud Platform and published APls
  • D. Context-aware SAP S/4HANA extensions, focused on tight integration

Answer: C

 

NEW QUESTION 22
In which phase will the customer develop a preliminary strategy for building a target Operations and Support organizational model?
Please choose the correct answer.
Response:

  • A. Explore phase
  • B. Run phase
  • C. Discover phase
  • D. Prepare phase

Answer: D

 

NEW QUESTION 23
In which phase of the SAP Activate methodology does the team complete the Transformation Planning?
Please choose the correct answer.
Response:

  • A. Prepare
  • B. Deploy
  • C. Explore
  • D. Realize

Answer: D

 

NEW QUESTION 24
What are some of the key characteristics of the implementation approach in SAP Activate Methodology?
There are 3 correct answers to this question.
Response:

  • A. Based on Ready-to-use Content
  • B. Delta-based
  • C. Cloud Ready
  • D. Fixed scope
  • E. On premise only

Answer: A,B,C

 

NEW QUESTION 25
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
Please choose the correct answer.
Response:

  • A. Go-Live scope is fixed on the first of January the following year.
  • B. Project scope and planning are completed and final.
  • C. User Stories are in a Ready state for NO more than the first three Sprints.
  • D. Timelines of the Sprint may differ due to the workload.

Answer: C

 

NEW QUESTION 26
Which of the following activities are part of the Deploy Phase of a Landscape Transformation journey to SAP S/4HANA On-Premise Edition?
There are 2 correct answers to this question.
Response:

  • A. Training delivery
  • B. Access organizational and production readiness
  • C. Solution Activation
  • D. Optimize software Change Control Management

Answer: A,B

 

NEW QUESTION 27
What technique helps a Scrum Team to prioritize a large, flat Backlog?
Please choose the correct answer.
Response:

  • A. Planning Poker
  • B. Retrospective
  • C. Fit/Gap Analysis
  • D. User Story Mapping

Answer: D

 

NEW QUESTION 28
What information does the product team need so that they can estimate the relative size of backlog user story correctly?
Please choose the correct answer.
Response:

  • A. Available project resources
  • B. Overall project schedule
  • C. Test strategy
  • D. Definition of Done

Answer: D

 

NEW QUESTION 29
Which of the following is not correct about workstreams?
There are 2 correct answers to this question.
Response:

  • A. Workstreams are dependent on phase start and end
  • B. It is a collection of related deliverables
  • C. It is assigned as an attribute to phases, deliverables and tasks
  • D. It can span phases

Answer: A,C

 

NEW QUESTION 30
What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition?
Please choose the correct answer.
Response:

  • A. Limited involvement of business stakeholders
  • B. Start with executable content
  • C. Design-based
  • D. Waterfall approach

Answer: B

 

NEW QUESTION 31
Which artifacts are part of the Solution Adoption work stream?
There are 3 correct answers to this question.
Response:

  • A. Project Business Case
  • B. Business Transformation Review (Point of View)
  • C. Project Plan
  • D. Detailed Design - Business Process
  • E. System Go live Announcement (order)

Answer: A,B,E

 

NEW QUESTION 32
Where can you find the Integration Content?
There are 3 correct answers to this question.
Response:

  • A. SAP Best Practices Explorer
  • B. Cloud Integration Automation Service
  • C. SAP Cloud Appliance library
  • D. SAP Solution Manager
  • E. SAP API Business Hub

Answer: A,B,E

 