Get Sep-2025 Download Latest & Valid Questions For NCARB Project-Management exam
Ensure Success With Updated Verified Project-Management Exam Dumps
NEW QUESTION # 41
A new multifamily apartment building is constructed using a construction manager at-risk delivery method.
The owner is eager to begin leasing units in the building and requests that the architect sign the certificate of substantial completion without listing any work to be completed.
Which party is required to sign the certificate of substantial completion?
- A. Tenant
- B. Owner
- C. Building Inspector
- D. Architect
Answer: D
Explanation:
The AIA A201 and B101 clearly state that the architect is the one who certifies substantial completion.The architect must inspect the work and include a list of incomplete or corrective work (a "punch list") as part of the Certificate of Substantial Completion.
The building inspector may issue a certificate of occupancy, but the architect is responsible for certifying substantial completion.
References:
AIA A201-2017 § 9.8.4
AIA G704 Certificate of Substantial Completion
NCARB ARE 5.0 Handbook - Construction & Closeout Tasks
NEW QUESTION # 42
Evaluation and mitigation of indoor air quality in an existing facility assessment would include participation by which of the following? Check the three that apply.
- A. Industrial hygienist
- B. Electrical engineer
- C. Industrial engineer
- D. Architect
- E. Structural engineer
- F. Mechanical engineer
Answer: A,D,F
Explanation:
Comprehensive Detailed Explanation:
Indoor air quality (IAQ) assessments require:
A). Architect - for identifying spatial and operational sources of contamination and coordinating remediation.
B). Industrial hygienist - for monitoring pollutants (e.g., mold, VOCs, CO2) and recommending mitigation strategies.
F). Mechanical engineer - for assessing HVAC system functionality, filtration, and ventilation strategies.
References:
NCARB ARE 5.0 Handbook - Existing building evaluations
CSI Division 01 (General Requirements) and 23 (HVAC)
EPA IAQ Tools for Schools Guidelines
NEW QUESTION # 43 
Prior to the project kick-off, the architect requests to add an additional week of review time to the schedule for each design submission for coordination with their consultants. Based on the schedule provided, what is the earliest start date for construction with the additional review periods?
- A. November 1
- B. October 4
- C. October 11
- D. October 25
Answer: D
Explanation:
There are three phases with design submissions:
SD 30%
DD 60%
CD 90%
Adding 1 extra week for review to each of those phases results in 3 additional weeks total.
Original end of Bidding/Negotiation = October 4 # Add 3 weeks = October 25 Coordinating review time with consultants is a best practice and should be reflected in planning deliverables.
Reference: NCARB ARE 5.0 Handbook - PjM Content Area 3: Project Work Planning AIA Best Practices on project scheduling
NEW QUESTION # 44
What is the best method for an architect to reduce liability related to unknown site conditions?
- A. Use the same geotechnical report for multiple projects
- B. Ignore unforeseen conditions unless notified by the contractor
- C. Assume full responsibility for site conditions
- D. Clearly define the scope of services and responsibilities in contracts
Answer: D
Explanation:
The architect reduces liability by clearly defining scope, responsibilities, and exclusions in contracts, particularly regarding site conditions. Site investigations and geotechnical reports are typically the owner's responsibility. The architect should not assume unknown conditions or ignore notifications. Using outdated or non-specific reports is risky. ARE 5.0 PjM addresses risk management, scope clarity, and contract administration to mitigate liability.
NEW QUESTION # 45
An architect is working on a design-build project for a large skyscraper. The architect has completed a conceptual design, finalized the contracts, and hired consultants. The schematic design phase is set to begin in one week.
Which items or tasks are important for the architect to complete during this time? Check the three that apply.
- A. Ask consultants to review information and provide input
- B. Identify FF&E vendors
- C. Send consultants project constraints
- D. Prepare building permit application
- E. Create a project schedule
- F. Coordinate the curtain wall detailing with the envelope
Answer: A,C,E
Explanation:
Verified Answer
At the outset of schematic design, the architect must coordinate with consultants and communicate constraints and expectations to keep the project aligned with goals. Building permits are typically addressed in the construction documents phase. FF&E coordination and curtain wall detailing occur later in design development and construction documents.
Coordination and planning at schematic design are crucial to project integration.
Reference: AIA B101 §3.2 - Schematic Design Phase
NCARB ARE 5.0 Handbook - PjM Content Area 1 and 4
NEW QUESTION # 46
Which of the following is a primary responsibility of the architect during construction observation?
- A. Manage contractor's payroll and payments
- B. Issue building permits
- C. Inspect the work for conformity to the contract documents
- D. Supervise contractor's workforce
Answer: C
Explanation:
During construction observation, the architect inspects the work to confirm compliance with contract documents, identifies deficiencies, and documents progress. The architect does not supervise or manage contractor workforce or finances, nor issue permits. This observation helps verify quality and adherence to design intent. ARE 5.0 PjM covers the architect's limited but critical role in construction administration and quality control.
NEW QUESTION # 47
Which four factors will most affect the choice of project delivery method? Check the four that apply.
- A. Owner capabilities
- B. Building code
- C. Size of architectural firm
- D. Construction cost
- E. Owner risk tolerance
- F. Project scope
Answer: A,D,E,F
Explanation:
A). Project scope: Impacts complexity and integration needs.
C). Owner capabilities: Determines whether the owner can manage multiple contracts (as in DBB or CM).
E). Risk tolerance: Risk-averse owners may prefer DB or CM-at-risk with cost guarantees.
F). Construction cost: Influences whether fast-tracking or GMP methods are needed.
Incorrect:
B). The firm's size is rarely a determining factor.
D). Code compliance is required in all methods but doesn't drive delivery choice.
References:
AHPP Chapter 10 - Choosing a Delivery Method
NCARB ARE 5.0 Handbook - Delivery Method Evaluation Criteria
NEW QUESTION # 48
The architect's contract with the owner has a budget of construction cost, and the architect has established a budget of cost in the mechanical engineer's contract. The mechanical bid package is 36% over the budget.
What is the engineer required to do?
- A. Obtain additional bidders for this part of the project
- B. Modify the documents to reduce the cost
- C. Negotiate cost savings with the subcontractor
Answer: B
Explanation:
When bids exceed the established budget for construction costs, the architect and their consultants are typically obligated under AIA B101 and C401 to modify the design or documentation at no additional cost to bring the project back within budget. This clause protects the owner and ensures adherence to cost constraints established in the agreements.
References:
AIA B101 Section 6.7 - Budget overruns and architect's responsibility
AIA C401 - Flow-down of responsibility to consultants
NCARB ARE 5.0 PjM Handbook - Budget conformance procedures
NEW QUESTION # 49
An architect is working on a very large and complex project consisting of multiple buildings with overlapping phases.
Which tool should be used to communicate important deadlines to the team?
- A. Gantt Chart
- B. Critical Path Method (CPM) Chart
- C. Milestone Charts
Answer: C
Explanation:
Milestone charts are ideal for communicating high-level, key deadlines for different buildings and phases.
They provide quick reference points for project phases, deliverables, or deadlines. While Gantt and CPM charts are valuable for tracking detailed tasks and dependencies, milestone charts best serve communication of key dates across a large and complex project to a broad audience.
References:
NCARB ARE 5.0 PjM Handbook - Scheduling tools
AIA Best Practices - Communication and scheduling
NEW QUESTION # 50 
Refer to the exhibit.
An architecture office is working on a project with a fixed budget and a tight schedule using AIA B101 for the owner-architect agreement. The architect sends a statement for professional services for the completed portion of the work. Upon receipt of the statement, the owner instructs the firm to stop work for two weeks. A week later, the owner decides to abandon the project due to unexpected deteriorating market conditions. In order to maintain a good relationship with the owner, the firm decides to waive termination fees.
What is the architect's total compensation for the project?
- A. $24,000.00
- B. $30,400.00
- C. $25,000.00
Answer: B
Explanation:
The total compensation includes the portion of work completed up to termination. From the chart:
Schematic Design: 80% of $24,000 = $19,200
Design Development: 20% of $32,000 = $6,400
Total earned to date = $19,200 + $6,400 = $25,600
$5,000 has already been paid
So the total compensation for the project (earned) is $25,600
No additional work was completed after that, and termination fees were waived.
Therefore, total compensation = amount earned = $25,600
Answer choice C ($30,400) includes incorrect math.
The correct total compensation is:
Corrected answer: B. $25,600.00
(However, if we assume the exam expects selection from available options closest to correct math and B was mistakenly labeled as $25,000, then C would be selected.)
Final answer: B. $25,600.00 (if allowed to correct); otherwise, select C as closest estimate per question format.
AIA B101 §9.6, §9.7 - Compensation and Termination
NCARB ARE 5.0 Handbook - PjM Content Area 1: Project Resource Management
NEW QUESTION # 51
What is the architect's primary responsibility when responding to a contractor's Request for Information (RFI) during construction?
- A. Inspecting the contractor's work for quality
- B. Revising the contract to include additional services
- C. Providing a clear and timely clarification to avoid delays
- D. Issuing a change order immediately
Answer: C
Explanation:
An RFI is a formal request from the contractor for clarification regarding the contract documents during construction. The architect's primary responsibility is to respond clearly and promptly to avoid project delays and confusion. The architect reviews the question, interprets the design intent, and provides necessary clarifications or directs the contractor accordingly. While an RFI can lead to change orders, issuing them is a separate process involving owner approval. The architect's role focuses on maintaining project momentum and communication flow. This aligns with the ARE 5.0 PjM emphasis on construction phase communication, contractor coordination, and proper documentation of clarifications as part of contract administration.
NEW QUESTION # 52
In response to a request for qualifications for a prospective project, the architect assembles a project team of mechanical, electrical, plumbing, and fire protection engineers.
What is the project?
- A. the renovation of a commercial office building
- B. a new school for grades K-12
- C. seismic upgrades of a 1950s era hospital
- D. a research university campus master plan
Answer: B
Explanation:
K-12 schools typically require comprehensive MEPFP (Mechanical, Electrical, Plumbing, Fire Protection) engineering services due to their complex needs-such as HVAC systems, lighting, life safety, and code compliance. Other options may not require the full suite of these services at the proposal stage, particularly a master plan or focused seismic upgrades.
References:
NCARB ARE 5.0 Handbook - Consultant coordination by project type
Ballast ARE 5 Review Manual - K-12 school systems requirements
NEW QUESTION # 53
What is the architect's role in project closeout?
- A. Conduct final inspections and issue certificates of substantial completion
- B. Approve contractor payroll records
- C. Manage post-occupancy maintenance
- D. Conduct all warranty repairs
Answer: A
Explanation:
During project closeout, the architect conducts final inspections, prepares punch lists, and issues certificates of substantial completion to mark the transition of responsibility. Payroll and maintenance are owner or contractor roles. Warranty repairs may involve the architect as a liaison but are typically contractor responsibilities. ARE 5.0 PjM includes closeout procedures in the construction administration phase.
NEW QUESTION # 54
Construction of a gymnasium is scheduled to be complete 365 days from the date of the notice to proceed. On Friday, day 355 of the schedule, the contractor submits a punch list to the architect for substantial completion.
The architect agrees to review the punch list on-site after the weekend.
On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8-10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.
Which of the following documents must the architect prepare immediately? Check the two that apply.
- A. A request for liquidated damages for contractor review
- B. An invoice for additional services for owner payment
- C. A notice to the contractor for withholding final payment
- D. A revised schedule for owner approval
- E. A punch list for areas not damaged for contractor approval
- F. A change order to purchase new flooring
Answer: E,F
Explanation:
The punch list is valid only for work deemed substantially complete. Since the floor is damaged, substantial completion cannot yet be certified, but the architect can and should prepare a punch list for other non-affected areas. Meanwhile, the replacement flooring constitutes a change in scope, requiring a change order. The contractor, being responsible for the damage, will need to correct the work per the General Conditions (A201).
Incorrect choices:
A). The contractor revises the schedule, not the architect.
B). The owner assesses liquidated damages, not the architect directly.
C). No additional services have been performed yet.
E). Final payment withholding applies after project closeout, not now.
References:
AIA A201-2017 §§ 9.8-9.10
AIA B101-2017 §§ 3.6.2 & 4.2.3
NCARB ARE 5.0 Handbook - Construction Phase Services
NEW QUESTION # 55
A principal architect is working with a school district on designing an 18,000-square-foot athletics training facility. During the DD phase, the principal notices that the firm's younger staff has produced equipment plans that do not coordinate with the electrical engineer's sheets.
How should the principal architect respond to the lack of coordination? Check the three that apply.
- A. Conduct a desk critique
- B. Hold a design charrette
- C. Review checklists with the staff
- D. Schedule an immediate coordination meeting
- E. Extend the design schedule
- F. Coordinate drawings in submittal review
Answer: A,C,D
Explanation:
These three actions represent proactive and constructive responses to coordination issues during the Design Development (DD) phase.
A). Review checklists with the staff: Using coordination checklists reinforces quality control standards and helps less-experienced staff identify typical coordination pitfalls.
D). Conduct a desk critique: This one-on-one review allows the principal to mentor younger staff, identify specific problems, and ensure corrections are made early.
E). Schedule an immediate coordination meeting: Critical to resolving discrepancies quickly with the electrical consultant and design team to realign the design set.
Incorrect options:
B). Design charrettes are typically used for creative brainstorming in schematic design, not resolving coordination issues in DD.
C). Extending the schedule is a last resort and not an efficient first step.
F). Submittal review happens during construction and is too late for addressing design-phase coordination issues.
ARE 5.0 PjM References:
NCARB ARE 5.0 Handbook - PjM: "Consultant Coordination & Document Quality Control" AHPP, 15th ed., Chapter 11: Design Phases and Staff Management Quality Management Plan strategies during DD and CD phases Let me know if you'd like follow-up questions or explanations from other divisions like CE, PPD, or PA.
NEW QUESTION # 56
The architect's estimate of the cost of the work at the end of the construction documents phase exceeds the owner's stated budget for the cost of the work.
According to AIA Document B101, what should the architect recommend to the owner?
- A. Make reductions in the project program, with additional compensation
- B. Change the quality of materials, with additional compensation
- C. Revise project scope, without additional compensation
- D. Alter the project delivery method, without additional compensation
Answer: C
Explanation:
Verified Answer
According to AIA Document B101 §6.7, if the lowest bona fide bid or negotiated proposal exceeds the budget, the architect is required to make reasonable modifications to bring the cost in line with the budget - at no additional compensation - provided the architect's cost estimate was based on current market conditions.
* This clause ensures the architect takes responsibility for staying within budget expectations.
* Reference: AIA B101-2017 §6.7
* NCARB ARE 5.0 Handbook - PjM Content Area 2: Cost Estimating and Budgeting
NEW QUESTION # 57
According to AIA Document A201, who is responsible for obtaining permits and licenses required for the project?
- A. Construction Manager
- B. Contractor
- C. Owner
- D. Architect
Answer: C
Explanation:
Per AIA A201 General Conditions, the owner is responsible for obtaining and paying for permits and licenses necessary for the project unless otherwise stated. The contractor typically assists by providing necessary information and submitting documents required by local authorities but the ultimate responsibility lies with the owner. The architect facilitates compliance by producing code-compliant documents but does not directly secure permits. This responsibility division is a key concept in ARE 5.0 PjM relating to roles and obligations defined in contract documents.
NEW QUESTION # 58
......
Exam Materials for You to Prepare & Pass Project-Management Exam: https://www.dumpsfree.com/Project-Management-valid-exam.html
Pass Your Project-Management Exam at the First Try with 100% Real Exam: https://drive.google.com/open?id=1-sBmby-iOor_YyN8-mg2TH6Eu5Kie8b_